The University of British Columbia established in 1908, consists of a diverse collection of academic, research, residential, and institutional buildings developed over more than a century ago. The campus includes a mix of historic and modern facilities, with ongoing construction and redevelopment projects focused on expanding research capacity, improving student services, and supporting future growth.

ProjectUBCClientEnersolv Design + BuildProject TypeNew Construction – Institutional - ResidentialLocationVancouver, BCServices ProvidedCxShare

Goal of the project

The project delivered two new buildings at UBC’s Lots 5 & 6 — an 18-storey tower and a 6-storey mass timber mid-rise — providing staff and student housing. Heating for both buildings is supplied by the UBC district energy system through an existing energy transfer station on site, with an air-cooled chiller on the roof of each building serving cooling loads. With the buildings leased for September 2025 occupancy, the commissioning programme had to be delivered on a fixed and immovable schedule, across a large quantity of mechanical devices and extensive BACnet networks extending to a thermostat controller in every suite.

How did KCx achieve goal

The combination of device count and schedule made conventional sequential testing impractical. KCx Engineering addressed this by batching commissioning tests to run overnight, with automated pass/fail evaluation and diagnostics generated from the data recorded during each test — a data-driven process facilitated by the platform developed with our sister company, clistek.io.

This approach allowed our team to execute testing remotely and at scale — covering the full population of suite controllers and mechanical devices across both buildings without extending the programme or compressing the quality of verification. Rather than sampling or accepting reduced coverage to meet the date, every test produced a recorded data set and a documented result.

Both buildings were commissioned in time for the September 2025 occupancy date, with the district energy connection, building-level cooling plants, and suite-level controls verified as operating to design intent.